Dam construction completed for 99.5-MW Karakurt hydro plant in Turkey

ENERGO-PRO’s Turkish subsidiary announced
it completed construction of the Karakurt Dam, including the construction of part
of the power plant, at the beginning of this year and started filling the
reservoir this week.

The dam for the 99.5-MW Karakurt hydro plant on the Aras River in eastern Turkey is ranked among the highest asphalt-core dams in the world, ENERGO-PRO says. The dam is 137 meters high, and construction started in 2017. To build the dam, 6.4 million cubic meters of rock was needed, and 30,500 cubic meters of asphalt mixture were consumed on the asphalt core itself.

“This technology is still very
rarely used in Turkey, as the laying of asphalt requires considerable precision
both in the design of the mix and in the construction itself. In this respect,
the investor plays an important role and must have the whole process closely
monitored,” said Celal Kozumali, director of ENERGO-PRO Turkey.

“Karakurt will be one of our three
largest power plants. It is also an important reference for us, we were able to
complete the construction according to the timetable and with significant
financial savings compared to the original prognosis,” said Pavel Váňa, chief
executive officer of the Prague-based ENERGO-PRO Group.

Construction of the power plant
started in 2018. The plant will be connected by two electric lines. The first
is 7 km long, the second 40 km. Up to 1,200 workers were working on site during
peak times of the dam and power plant construction, and the work was carried
out in shifts 24 hours 7 days a week.

ENERGO-PRO says about 1,000 people
had to be evicted due to the construction of the dam and power plant. The
company’s purchase of land and resettlement costs amounted to nearly US$21
million.

Other companies from the ENERGO-PRO
group participating in the construction of the Karakurt hydroelectric plant:
Litostroj Turkey manufactured the impellers and spiral cases for the three
Francis turbines, as well as the generators; and Litostroj Engineering
(formerly ČKD Blansko Engineering) designed the turbines and generators.

The total estimated costs of the
project are now around US$220 million.

The project is in its final stage. In
the coming months, the mechanical and electrical parts in the power plant,
injection work to seal the rock massif in the immediate vicinity of the dam,
relocation of roads and cable lines remain to be completed. Filling of the dam is
expected to take up to six months, and the first turbine will be tested in May.

This year, the ENERGO-PRO Group will also finalize the construction of another hydroelectric power plant in eastern Turkey – 280-MW Alpaslan 2.

Turkey considers the construction of
new water resources to be one of the main ways to get rid of dependence on
energy imports. The Turkish government expects that energy demand will increase
due to long-term economic development and despite the country’s economic
problems in recent years.

A study by the University of
Economics in Izmir has shown that hydroelectric power plants are the most
suitable energy source for Turkey. Their share in the total installed capacity
of Turkish power plants is already over 30%. By supporting investment in the
past decade, Turkey has managed to significantly increase its share of domestic
energy sources, which account for up to two-thirds of electricity production.

Leave a Reply

Your email address will not be published. Required fields are marked *


Search Solar News and Articles on The Solar Move: